VA Drops Millions on Delayed Solar Power Projects. VA has spent over $408 million on
solar panels since 2010. Workers assemble solar power units at the Salem Veterans
Affairs Medical Center in Salem, Va. / AP BY: Morgan Chalfant, 8/8/16
The Department of Veterans Affairs
has spent more than $408 million to install solar panels on its medical
facilities in recent years, despite many of the projects experiencing
significant delays and some of the systems not becoming operational at all.
The VA has failed to effectively
plan and manage these solar panel projects, resulting in significant delays and
additional costs, according to a report released by the agency’s inspector general last week.
The watchdog conducted an audit of
11 of the 15 solar projects awarded between fiscal years 2010 and 2013 that
were still in progress as of May last year. The investigation, which was
completed in March, found that only two of the 11 solar panel projects were
fully completed.
“This occurred because of planning
errors, design changes, a lengthy interconnection process, and contractor
delays,” the inspector general concluded. “As a result, VA did not increase
renewable energy for those solar projects in the time frame planned and
incurred additional costs through needed contract modifications.”
The VA subsequently told the
inspector general in July that five of the 11 projects had been fully completed
and eight were generating solar power. Three of the planned systems, including
one in Little Rock, Arkansas, that precipitated the investigation, still are not
generating solar power at all.
According to investigators, all of
the projects were supposed to be finished in about seven to 12 months but
instead were completed—or remain expected to be completed—on average, within 42
months.
The contracts for the 11 projects
reviewed by investigators totaled about $95 million, though some have become
more expensive because of poor planning and delays. The VA spent more than $408
million on its “green management program” solar panel projects between fiscal
years 2010 and 2015, according to annual budget records. During the same
period, veterans died waiting for care at VA hospitals where employees were
using dishonest record keeping practices to conceal long waits for care.
The inspector general initiated the
investigation at the request of Arkansas Sens. John Boozman and French Hill,
both Republicans, who asked the watchdog to examine a significantly delayed $8
million solar panel project at the John L. McClellan Memorial Veterans Hospital
in Little Rock last April.
The project, begun in 2012, has been
delayed more than four years beyond its original planned completion date and
will cost taxpayers an additional $1.5 million. The VA spent millions to
install the solar panels at the Little Rock facility in 2013, only to remove
and reinstall them two years later to accommodate a new parking garage. To add
to problems, the panels were never turned on because they were incompatible
with the local electric grid.
The VA has set aside nearly $1
million to disassemble and reassemble the panels and will spend roughly
$350,000 on changes to the equipment, according to the audit.
“The Little Rock officials did not
effectively plan the installation of the system and a determination regarding
whether expected solar power generation was achieved could not be made as the
system has yet to be activated,” the inspector general wrote.
“The project experienced significant
delays and additional contract costs due to disassembly of previously installed
solar panel carport structures to accommodate a parking garage. In addition, a
lengthy interconnection agreement process with the local private utility and
contractor performance issues added to the delays.”
The VA said the watchdog was
“biased” in its review because the audit only covered solar panel projects that
were in progress during the scope period and not those that had been completed,
according to the report. VA officials also said that the Little Rock project
was “complex” because of the planned parking garage construction, which was
approved and finalized after the solar panel contract was awarded.
Both Boozman and Hill called for
increased oversight of VA green management programs in the future to avoid
failures.
“Whether it is a project as complex
as hospital construction or one as simple as the proper installation of solar
panels, VA continues to waste large amounts of taxpayer funds as a result of
its own ineptitude,” Hill said in a statement.
The VA has been under fire for
wasting federal dollars as veterans’ wait times and other failings have
persisted at the agency’s network of medical facilities. A recent investigation by Open the Books and COX Media revealed that the VA spent
$20 million on artwork over the last decade, outraging members of Congress.
http://freebeacon.com/issues/va-drops-millions-delayed-solar-power-projects/